Back to projects

Pant Y Wal Wind Farm

Pant Y Wal Wind Farm

The steel fixing for this project was awarded to iFix Reinforcements Ltd by Euro Construction in February 2012. There were a total of 21 turbine bases in this project with a total of 840 tonne. Each turbine base was completed with 4 steel fixers with in 4-5 working days, with a gap in that period to fit the can. These turbine bases were a very technical and difficult fixing process. With very bad weather conditions from start to finish. iFix Reinforcements Ltd fixed within the programme week in week out, with no accidents or defaults.



Walters UK

Pant Y Wal Wind Farm


Gilfach Goch


Back to projects