Circan Farm Wind Turbine Base

Circan Farm Wind Turbine Base

This single Wind Turbine Base to be constructed and Circan Farm was awarded to iFix Reinforcements Ltd by HOS Ltd.

 As with construction of any Wind Turbine Base, time is of the essence.  This project with a total of 20 tonne was completed in three days by one of our professional steel fixing teams that was made up of 3 men.  This process was managed as follow; 1 day Bottom Mat reinforcement,1 day Can reinforcement and1 day top mat reinforcement. iFix reinforcements Ltd also placed the external shuttering for this project.  It was a pekafil system and was completed on the third day of construction.



HOS

Circan Farm Wind Turbine Base


Camarthen