Wells Cathedral School has undergone the construction of Cedars Hall, the new theatre building. This project will greatly improve the prospects for education within Wells Cathedral School and also the community as a whole.
iFix Reinforcements Ltd had an integral part as we completed the steel fixing contract for the subterranean foundations for the new theatre.
There was a total of 62 tonnes of rebar placed within the foundations over a 4 week period with a team of 4 steel fixers.
It was a challenging project due to a tight program, however iFix’s professional team of steel fixers were able to manage and complete the project on time!